Which of the following should a project manager update to document this information?

A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the datacenter project is out on medical leave.

Which of the following should a project manager update to document this information?
A . A list of realized risks
B . A list of decomposed activities
C . A sequenced list of project tasks
D . A document describing agreed-upon communication methods

Answer: A

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 240

Latest PK0-004 Dumps Valid Version with 323 Q&As

Latest And Valid Q&A | 90 Days Free Update | Once Fail, Full Refund

Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>

  • Sign up
Lost your password? Please enter your username or email address. You will receive a link to create a new password via email.
We do not share your personal details with anyone.