Which of the following should the project manager do NEXT?

A project sponsor informs the project manager that the project completion date must be moved one month earlier .

Which of the following should the project manager do NEXT?
A . Recalculate the critical path, determine the new cost, schedule baselines, and initiate the change request process.
B . Recalculate the schedule and cost variance, and report the changes to the project stakeholders and sponsor.
C . Calculate the cost of crashing the schedule, and obtain the stakeholders’ approval for the new project WBS and timeline.
D . Calculate the additional resource requirements that are necessary to meet the new project deadline, and work with human resources to hire additional staff.

Answer: B