Which of the following BEST describes these projects?

A company has completed its annual strategic planning session. As a result, several related projects, which will achieve the company’s technological improvement goals, are identified .

Which of the following BEST describes these projects?
A . Portfolio
B . Program
C . Deliverable
D . Outcome

Answer: B