Which of the following documents will the company MOST likely release FIRST?

A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services.

Which of the following documents will the company MOST likely release FIRST?
A . RFO
B . RFI
C . RFP
D . RFQ

Answer: B

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 300

Latest PK0-004 Dumps Valid Version with 323 Q&As

Latest And Valid Q&A | 90 Days Free Update | Once Fail, Full Refund

Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>

  • Sign up
Lost your password? Please enter your username or email address. You will receive a link to create a new password via email.
We do not share your personal details with anyone.