What should the project manager do?

During the implementation stage of a project. a newly appointed team leader approaches the project manager to verify the team’s tasks and schedule. The work did not go as planned due to the team leader’s lack of management experience. This could cause delays for the project.

What should the project manager do?
A . Ask the human resources director to appoint a senior team leader
B . Inform the project sponsor about the possible delay
C . Directly manage the project team to avoid project delays
D . Provide mentoring to the newly appointed team leader

Answer: D

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments