What should the project manager do?

The programming activities of a project were planned to last 35 days per module but the programming of the first module has taken 45 days.

What should the project manager do?
A . Ask the team to work overtime to complete the deliverable on time
B . Evaluate the situation and identify ways to compress the schedule without impacting baselines
C . Check the scope to verify if there is scope creep and get the project on schedule
D . Submit a change request to the project sponsor to change the schedule

Answer: B

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments