Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time.
Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time.
Starting Task B prior to Task A completing is an example of:
A . Managing change
B . Fast tracking
C . Rolling wave planning
D . Crashing
Answer: B