What should the project manager do in this situation?

At the end of a meeting a functional manager takes the project manager aside to raise some concerns on behalf of a project team member who is unclear about their role and responsibilities for the project. What should the project manager do in this situation?A . Develop a work plan...

May 27, 2022 No Comments READ MORE +

How should the project manager assist the product owner?

A company is implementing a new system. The project manager has identified that it is best to complete this project using a mix of Scrum and Kanban methodologies. The product owner is confused as to how to start delivering the functionalities required How should the project manager assist the product...

May 27, 2022 No Comments READ MORE +

What two actions should the project manager take?

A team member shares with their functional manager some negative details about the performance of another team member that was discussed during the retrospective. The project manager finds out about this discussion What two actions should the project manager take? (Choose two)A . Contact the team member's functional manager and...

May 26, 2022 No Comments READ MORE +

How should the project manager acknowledge this team member’s commitment?

One of a project manager’s team members is continuously improving This team member has been a role model and mentor to others in the organization How should the project manager acknowledge this team member’s commitment?A . Send this person to a meeting to negotiate the scope with the clientB ....

May 26, 2022 No Comments READ MORE +

What factor should the project manager consider when determining if the project is suitable for an agile approach?

An executive sponsor of a predictive project asked a project manager experienced in agile to assess if a project could be executed using an agile approach. What factor should the project manager consider when determining if the project is suitable for an agile approach?A . The project is an information...

May 26, 2022 No Comments READ MORE +

An agile team is geographically separated across multiple continents, and the project manager of identifying the tools to manage the communication among the virtual teams

DRAG DROP An agile team is geographically separated across multiple continents, and the project manager of identifying the tools to manage the communication among the virtual teams. Drag the appropriate tool on the left to each project task on the right View AnswerAnswer:

May 26, 2022 No Comments READ MORE +

A project manager receives an update that the development flow is not going well. Some team members cannot start their work because the delivery is late. Looking at the Kanban board and the work in progress (WIP) lines, the project manager observes a bottleneck

HOTSPOT A project manager receives an update that the development flow is not going well. Some team members cannot start their work because the delivery is late. Looking at the Kanban board and the work in progress (WIP) lines, the project manager observes a bottleneck. Click the title of the...

May 26, 2022 No Comments READ MORE +

What two actions should the project manager take'?

A large project is affecting the neighborhood in which it is located. The neighbors are not satisfied with the project and their resistance to the project may affect the project deadline What two actions should the project manager take'? (Choose two)A . Send letters to the neighbors and ask them...

May 26, 2022 No Comments READ MORE +

What artifact should the project manager share with the stakeholder?

The project manager is reviewing the program risks and issues with key stakeholders One of the stakeholders wants to understand when the risk may potentially become an issue . What artifact should the project manager share with the stakeholder?A . Issue logB . Project management planC . Risk management planD...

May 26, 2022 No Comments READ MORE +

During the development of a product, the project manager observes conflicts between project stakeholders, resulting in deliverable and output approval delays On which area should the project manager focus?

During the development of a product, the project manager observes conflicts between project stakeholders, resulting in deliverable and output approval delays On which area should the project manager focus?A . Revisiting the project management plan to ensure deliverables are on timeB . Increasing the frequency of project update meetings to...

May 25, 2022 No Comments READ MORE +