Which of the following would be the BEST source for the high-level project requirements?

A new project charter is being drafted. Which of the following would be the BEST source for the high-level project requirements?A . SponsorB . Project managerC . Project management officeD . Project teamView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 108

March 17, 2022 No Comments READ MORE +

Which of the following factors are MOST likely to influence communication methods selected for the communication plan?

A project team is spread between two countries on different continents. Which of the following factors are MOST likely to influence communication methods selected for the communication plan? (Select TWO).A . Interorganizational constraintsB . Personal preferencesC . Language barriersD . Cultural differencesE . Confidentiality constraintsView AnswerAnswer: C,D

March 17, 2022 No Comments READ MORE +

This type of analysis is an example of which of the following?

The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure. This type of analysis is an example of which of the following?A . Cost performance indexB . Risk mitigationC . Schedule varianceD . Cost varianceView AnswerAnswer:...

March 16, 2022 No Comments READ MORE +

Which of the following types of meetings should happen NEXT?

A project is about to begin the execution phase. The SOW and project plan have been approved, and the project team has been formed. Which of the following types of meetings should happen NEXT?A . UpdateB . SchedulingC . KickoffD . ReviewView AnswerAnswer: B

March 16, 2022 No Comments READ MORE +

Which of the following factors MOST likely needs to be accounted for when communicating with this stakeholder?

A critical stakeholder has requested additional status updated beyond the schedule. Which of the following factors MOST likely needs to be accounted for when communicating with this stakeholder?A . ConfidentialityB . CriticalityC . FrequencyD . Cultural differencesView AnswerAnswer: C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex,...

March 16, 2022 No Comments READ MORE +

Which of the following is the MOST effective method for providing these updates?

A project requires daily status updates. Which of the following is the MOST effective method for providing these updates?A . BacklogB . StandupC . KickoffD . RetrospectiveView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306

March 16, 2022 No Comments READ MORE +

Which of the following is MOST likely to be the first document created by the project manager?

A vendor has accepted a proposed project from a customer. Which of the following is MOST likely to be the first document created by the project manager?A . Project charterB . Project management planC . Project statement of workD . Project scheduleView AnswerAnswer: C Explanation: References: Kim Heldman, CompTIA Project+...

March 16, 2022 No Comments READ MORE +

Which of the following should have occurred to prevent this issue?

During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor’s tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the...

March 16, 2022 No Comments READ MORE +

Which of the following actions would be BEST for the project manager to take?

A project manager is managing a transactional project. One of the key team members is having difficulties understanding the client requirements. Which of the following actions would be BEST for the project manager to take?A . Ask the client to provide additional language resources to the team.B . Purchase a...

March 16, 2022 No Comments READ MORE +

Which of the following strategies has been applied?

A software upgrade project has been postponed because it may impact a critical business system. Which of the following strategies has been applied?A . Accept riskB . Mitigate riskC . Avoid riskD . Exploit riskView AnswerAnswer: C

March 16, 2022 No Comments READ MORE +