Which of the following should be used to complete the tasks on time?

A project manager does not have enough time to complete several tasks on a critical path. The budget is a low concern. Which of the following should be used to complete the tasks on time?A . Fast-track the tasks.B . Utilize positive float.C . Crash the schedule.D . Remove the...

March 18, 2022 No Comments READ MORE +

A project team has finished creating a WBS and started developing a schedule. The team should FIRST determine the:

A project team has finished creating a WBS and started developing a schedule. The team should FIRST determine the:A . durations.B . tasks.C . critical path.D . resources.View AnswerAnswer: B

March 18, 2022 No Comments READ MORE +

Which of the following is the BEST project management methodology for this requirement?

A customer will have ongoing changes to project requirements. Which of the following is the BEST project management methodology for this requirement?A . WaterfallB . AgileC . PRINCE2D . Bottom-upView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 310

March 18, 2022 No Comments READ MORE +

Which of the following describes how a project is related to a program?

Which of the following describes how a project is related to a program?A . A program is a combination of multiple projects.B . A program contains an element of the project.C . A program is a part of a project.D . A program uses half of the project’s budget.View AnswerAnswer:...

March 18, 2022 No Comments READ MORE +

A project has been experiencing some difficulties due to third-party vendors. The project manager should request.

A project has been experiencing some difficulties due to third-party vendors. The project manager should request.A . Additional resourcesB . A gate reviewC . A risk register updateD . A performance auditView AnswerAnswer: C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 272

March 17, 2022 No Comments READ MORE +

Which of the following factors will MOST likely influence the communication methods used in the project?

A project team is mainly based in a metropolitan area. The team also has members in a remote area, where Internet access is limited and unstable. Which of the following factors will MOST likely influence the communication methods used in the project?A . Personal preferencesB . Technological factorsC . Language...

March 17, 2022 No Comments READ MORE +

Which of the following documents need to be updated as events occur during a project? (Select TWO).

Which of the following documents need to be updated as events occur during a project? (Select TWO).A . Change requestB . Risk registerC . Meeting minutesD . Issue logE . Status reportView AnswerAnswer: C,E

March 17, 2022 No Comments READ MORE +

Which of the following is the BEST explanation?

A project manager is trying to explain to a stakeholder why projects are progressively elaborated upon. Which of the following is the BEST explanation?A . In the beginning, projects entail a degree of uncertainty that needs to be specified.B . In the beginning, projects have start and finish dates that...

March 17, 2022 No Comments READ MORE +

Which of the following is the BEST risk mitigation strategy that the project manager should use?

A project manager has identified a minor skills gap in the operational team that will end up supporting the project solution. Which of the following is the BEST risk mitigation strategy that the project manager should use?A . Organize adequate training and have one of the operational staff as part...

March 17, 2022 No Comments READ MORE +

Which of the following constraints does this impact MOST?

A non-stakeholder approaches the project manager and asks if certain items can be added to a project that was started two months earlier. Which of the following constraints does this impact MOST?A . TimeB . ScheduleC . ScopeD . CostView AnswerAnswer: D