Which of the following should have occurred to prevent this issue?
During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor’s tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the...
Which of the following should the project manager notify?
A milestone task on the critical path has been completed. Which of the following should the project manager notify?A . Owner of predecessor taskB . Project teamC . Project sponsorD . Project steering committeeView AnswerAnswer: C
Which of the following is a necessary step to record the actual durations?
A project manager needs to track the actual and estimated start and finish dates of all WBS work packages. Which of the following is a necessary step to record the actual durations?A . Establish each WBS work package resource.B . Establish and set the baseline.C . Establish and set the...