Which of the following documents should the project manager create?

A project manager is assigned to a new project that must start immediately. No formal or approved documents have been authored for the project. The project manager must identify project roles, justify the business need, and determine project scope boundaries. Which of the following documents should the project manager create?A...

October 26, 2019 No Comments READ MORE +

Which of the following is the NEXT step?

A project manager is justifying a required change with the associated impact on the project. Which of the following is the NEXT step?A . ImplementationB . ApprovalC . ValidationD . AuditingView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 294

October 26, 2019 No Comments READ MORE +

Which of the following steps should take place NEXT?

A customer has requested additional features for an active project. Which of the following steps should take place NEXT?A . Implement the requested changes.B . Evaluate the impact of the changes.C . Update all project documents.D . Submit the requested changes to the CCView AnswerAnswer: B Explanation: References: Kim Heldman,...

October 26, 2019 No Comments READ MORE +

Which of the following is a necessary step to record the actual durations?

A project manager needs to track the actual and estimated start and finish dates of all WBS work packages. Which of the following is a necessary step to record the actual durations?A . Establish each WBS work package resource.B . Establish and set the baseline.C . Establish and set the...

October 26, 2019 No Comments READ MORE +

Which of the following describes how the project manager should BEST determine the initial sequence and durations?

After identifying all known tasks, the project manager has started to sequence and set durations. Which of the following describes how the project manager should BEST determine the initial sequence and durations?A . Use milestones identified in the project charter.B . Use data based on past knowledge.C . Hold a...

October 26, 2019 No Comments READ MORE +

Which of the following techniques is MOST likely to be used to complete the project on time?

A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time. Which of the following techniques is MOST likely to be used to complete the project on time?A . ThrottlingB . CrashingC . Resource...

October 25, 2019 No Comments READ MORE +

Which of the following is a key aspect of the Agile project management methodology?

Which of the following is a key aspect of the Agile project management methodology?A . Test-drivenB . Daily standup meetingsC . Short project durationsD . Defined list of requirementsView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 286

October 25, 2019 No Comments READ MORE +

Which of the following should the project manager do to resolve this issue?

A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client. Which of the following should the project manager do to resolve this issue?A . Update the scope management plan.B . Modify the project baselines.C...

October 25, 2019 No Comments READ MORE +

Which of the following activities are associated with the closing phase of a project? (Choose two.)

Which of the following activities are associated with the closing phase of a project? (Choose two.)A . Risk mitigationB . Archiving of project documentsC . Tracking of expendituresD . Lessons learnedE . Quality assuranceView AnswerAnswer: B,D Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p....

October 24, 2019 No Comments READ MORE +

Which of the following is MOST likely to be the main challenge the influences this decision?

A project manager who is part of a global team wants to have a team building meeting and decides to hold a video conference. Which of the following is MOST likely to be the main challenge the influences this decision?A . Geographical factorsB . Language barriersC . Cultural differencesD ....

October 24, 2019 No Comments READ MORE +