Which of the following information should the project manager provide?
Maintenance estimates. Which of the following information should the project manager provide?A . Cost baselineB . Burn rateC . Cost variance reportD . Total project costView AnswerAnswer: A
Which of the following should the project manager bring to the meeting to support this recommendation?
The project manager was asked to provide recommendations for the removal of a vendor. A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation. Which of the following should the project manager bring to the meeting to support this recommendation? (Choose...
Which of the following best describes what the PM should work on FIRST?
The PM is preparing for the planning phase kickoff meeting. It is imperative for the team to focus during the meeting on the expected outcomes. Which of the following best describes what the PM should work on FIRST?A . Project charterB . Project scheduleC . Meeting agendaD . Responsibility assignment...
Which of the following steps can the project manager take to make the meetings more productive?
Team members have reported that meetings are poorly attended and unproductive. Which of the following steps can the project manager take to make the meetings more productive?A . Discontinue the meetings with the poorest attendance.B . Decrease the length of the meetings.C . Distribute an agenda before each meeting.D ....
Which of the following conflict resolution techniques has the project manager utilized?
Two team members have concluded that documentation is not required due to the size of the current project. The project manager has encouraged them to align strictly within the process. Which of the following conflict resolution techniques has the project manager utilized?A . SmoothingB . ForcingC . CompromisingD . AvoidingView...
Which of the following would indicate a project manager is working in a matrix-based organization?
Which of the following would indicate a project manager is working in a matrix-based organization?A . The project manager has full authority over resources and the project.B . The project manager has no authority over the project resources and limited-to-no authority over the project.C . Resources align to the project,...
Which of the following should the project manager do FIRST?
A team member was replaced on a project by a new team member of equal capability. Which of the following should the project manager do FIRST?A . Resource loadingB . Resource levelingC . Prioritizing tasksD . Allocating resourcesView AnswerAnswer: D
Which of the following elements should be included on a responsibility assignment matrix?
Which of the following elements should be included on a responsibility assignment matrix?A . Responsible, accountable, consulted, informedB . Resource, accountable, signoff, inputC . Responsible, accurate, confidential, informedD . Resource, accountable, consulted, informedView AnswerAnswer: A
Which of the following would be the MOST effective means to do this?
The project team is distributed throughout a single country. The scrum master has decided to hold remote "stand-ups" on a daily basis. Which of the following would be the MOST effective means to do this?A . Instant messagingB . Video conferenceC . Phone callD . Collaboration websiteView AnswerAnswer: B
Which of the following should the project manager notify?
A milestone task on the critical path has been completed. Which of the following should the project manager notify?A . Owner of predecessor taskB . Project teamC . Project sponsorD . Project steering committeeView AnswerAnswer: C