Which of the following should a project manager update to document this information?

A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the datacenter project is out on medical leave. Which of the following should a project...

November 6, 2019 No Comments READ MORE +

Which of the following would be BEST suited to contribute cost and time estimates for the project activities?

A WBS is being developed for a project. Which of the following would be BEST suited to contribute cost and time estimates for the project activities?A . Project team membersB . Project sponsorC . Project managerD . Project schedulerView AnswerAnswer: C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd...

November 6, 2019 No Comments READ MORE +

Which of the following constraints are MOST likely to be affected?

A project team is overseeing the installation of a new reptile habitat at the local zoo. During execution, zoo personnel decides to house a different type of reptile that will require a different temperature range than the capacity of the installed system. The modification has been approved. Which of the...

November 6, 2019 No Comments READ MORE +

In which of the following phases is the project?

A project manager is creating the WBS. In which of the following phases is the project?A . InitiationB . PlanningC . ExecutionD . ClosingView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 139

November 5, 2019 No Comments READ MORE +

Which of the following should a project manager update to document this information?

A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the datacenter project is out on medical leave. Which of the following should a project...

November 5, 2019 No Comments READ MORE +

Which of the following should have occurred to prevent this issue?

During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor’s tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the...

November 4, 2019 No Comments READ MORE +

Which of the following should a project manager update to document this information?

A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the datacenter project is out on medical leave. Which of the following should a project...

November 3, 2019 No Comments READ MORE +

Which of the following would be the MOST beneficial?

A project manager is attempting to establish the proper sequencing and duration of project activities. Which of the following would be the MOST beneficial?A . Network diagramB . Ishikawa diagramC . WBSD . Gantt chartView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017,...

November 3, 2019 No Comments READ MORE +

Which of the following are critical for the project manager to provide?

A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project. Which of the following are critical for the project manager to provide?A . Cost, schedule, organizational chart, and risks/issuesB . Risks/issues,...

November 3, 2019 No Comments READ MORE +

Which of the following tools is MOST appropriate for the project team to use to determine the cause of the problem?

One deliverable failed during testing, and this has already happened several times. Which of the following tools is MOST appropriate for the project team to use to determine the cause of the problem?A . Run chartB . Fishbone diagramC . Scatter diagramD . Gantt chartView AnswerAnswer: B Explanation: References: Kim...

November 3, 2019 No Comments READ MORE +