Which of the following should the project manager notify?
A milestone task on the critical path has been completed. Which of the following should the project manager notify?A . Owner of predecessor taskB . Project teamC . Project sponsorD . Project steering committeeView AnswerAnswer: C
Which of the following describes how a project is related to a program?
Which of the following describes how a project is related to a program?A . A program is a combination of multiple projects.B . A program contains an element of the project.C . A program is a part of a project.D . A program uses half of the project’s budget.View AnswerAnswer:...
Which of the following activities are associated with the closing phase of a project? (Choose two.)
Which of the following activities are associated with the closing phase of a project? (Choose two.)A . Risk mitigationB . Archiving of project documentsC . Tracking of expendituresD . Lessons learnedE . Quality assuranceView AnswerAnswer: BD Explanation: Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p....
Which of the following documents should be used to provide high-level reporting to key stakeholders?
Which of the following documents should be used to provide high-level reporting to key stakeholders?A . DashboardB . Communication planC . Statement of workD . Project charterView AnswerAnswer: A Explanation: Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 325
The PMO is responsible for: (Choose two.)
The PMO is responsible for: (Choose two.)A . managing the project plan, scope, risk, and budget.B . contributing expertise, deliverables, and estimates of costs.C . setting standards and practices for the organization and providing governance.D . outlining consequences of non-performance and coordinating between disparate projects.E . approving funding, developing the...
Which of the following meetings should be held to move to the NEXT step in the project?
The client accepts the critical design review. Which of the following meetings should be held to move to the NEXT step in the project?A . ExecutionB . KickoffC . ClosureD . PlanningView AnswerAnswer: B Explanation: Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 112
Which of the following actions would be BEST for the project manager to take?
A project manager is managing a transactional project. One of the key team members is having difficulties understanding the client requirements. Which of the following actions would be BEST for the project manager to take?A . Ask the client to provide additional language resources to the team.B . Purchase a...
Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option.
Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option. This type of conflict resolution is known as:A . forcing.B . avoiding.C . smoothing.D ....
Which of the following describes how the project manager should BEST determine the initial sequence and durations?
After identifying all known tasks, the project manager has started to sequence and set durations. Which of the following describes how the project manager should BEST determine the initial sequence and durations?A . Use milestones identified in the project charter.B . Use data based on past knowledge.C . Hold a...
Which of the following is the primary purpose of an MOA or an MOU?
Which of the following is the primary purpose of an MOA or an MOU?A . State expectations of all signatory parties to reduce potential misunderstandings.B . Facilitate potential legal action and resulting remediation if one of the signatory parties violates any terms.C . Enumerate a detailed code of conduct for...