Which of the following is a necessary step to record the actual durations?
A project manager needs to track the actual and estimated start and finish dates of all WBS work packages. Which of the following is a necessary step to record the actual durations?A . Establish each WBS work package resource.B . Establish and set the baseline.C . Establish and set the...
Which of the following are examples of organizational change? (Choose two.)
Which of the following are examples of organizational change? (Choose two.)A . RelocationB . ScopeC . Business processD . ScheduleE . Risk eventView AnswerAnswer: AC Explanation: Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 297
Which of the following documents would a project manager create to make team meetings more effective?
Several team members report that meeting objectives are not being met. Which of the following documents would a project manager create to make team meetings more effective? (Choose two.)A . Create an SOW prior to each meeting and adhere to it.B . Create a meeting agenda prior to each meeting...
Which of the following information should the project manager provide?
Maintenance estimates. Which of the following information should the project manager provide?A . Cost baselineB . Burn rateC . Cost variance reportD . Total project costView AnswerAnswer: A
Which of the following steps can the project manager take to make the meetings more productive?
Team members have reported that meetings are poorly attended and unproductive. Which of the following steps can the project manager take to make the meetings more productive?A . Discontinue the meetings with the poorest attendance.B . Decrease the length of the meetings.C . Distribute an agenda before each meeting.D ....
Which of the following are critical for the project manager to provide?
A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project. Which of the following are critical for the project manager to provide?A . Cost, schedule, organizational chart, and risks/issuesB . Risks/issues,...
Which of the following documents will the company MOST likely release FIRST?
A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services. Which of the following documents will the company MOST likely release FIRST?A . RFOB . RFIC . RFPD . RFQView AnswerAnswer: B Explanation: Reference: Kim Heldman, CompTIA Project+ Study...
Which of the following factors MOST likely needs to be accounted for when communication with this stakeholder?
A critical stakeholder has requested additional status updated beyond the schedule. Which of the following factors MOST likely needs to be accounted for when communication with this stakeholder?A . ConfidentialityB . CriticalityC . FrequencyD . Cultural differencesView AnswerAnswer: C Explanation: Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex,...
Which of the following should the project manager do NEXT?
The project manager for a TV tower construction project receives notification that a strong storm is expected the following week. Which of the following should the project manager do NEXT?A . Evaluate the risk, inform major stakeholders about the problem, and issue a change request immediately.B . Evaluate the risk,...
Which of the following should have occurred to prevent this issue?
During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor’s tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the...