Which of the following techniques is MOST likely to be used to complete the project on time?
A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time. Which of the following techniques is MOST likely to be used to complete the project on time?A . ThrottlingB . CrashingC . Resource...
Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?
During the execution phase of a project, a project task has run longer than anticipated. Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?A . 12 daysB . 14 daysC . 16 daysD . 19 daysView AnswerAnswer:...
Which of the following should the project manager do NEXT?
A project manager received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes. Which of the following should the project manager do NEXT?A . Gain approval for the changes.B . Identify the approval authority.C . Implement the changes.D . Create an...
Which of the following should the project manager bring to the meeting to support this recommendation?
The project manager was asked to provide recommendations for the removal of a vendor. A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation. Which of the following should the project manager bring to the meeting to support this recommendation? (Choose...
When a complex announcement needs to go out to the entire project team, which of the following is the MOST effective way to communicate it?
A project team is comprised of a mix of in-house and virtual team members. When a complex announcement needs to go out to the entire project team, which of the following is the MOST effective way to communicate it?A . Composing a project team email with the details of the...
Which of the following items should the project manager use to highlight the vendor’s areas of poor performance?
The project manager has noticed a vendor is not performing in accordance with the SLA. Which of the following items should the project manager use to highlight the vendor’s areas of poor performance? A. Balanced score card B. WBS C. Post-project evaluation D. PERTView AnswerAnswer: A Explanation: Reference: Kim Heldman,...
Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes?
A stakeholder is unaware of a project’s status. Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)A . Status reportB . Organizational chartC . RACI matrixD . Meeting minutesE . Communication planView AnswerAnswer: AD Explanation: Reference: Kim Heldman,...
Which of the following documents should the project manager create?
A project manager is assigned to a new project that must start immediately. No formal or approved documents have been authored for the project. The project manager must identify project roles, justify the business need, and determine project scope boundaries. Which of the following documents should the project manager create?A...
Which of the following would be the MOST beneficial?
A project manager is attempting to establish the proper sequencing and duration of project activities. Which of the following would be the MOST beneficial?A . Network diagramB . Ishikawa diagramC . WBSD . Gantt chartView AnswerAnswer: A Explanation: Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017,...
Which of the following terms describe this requirement?
A company has updated the method it uses to initiate projects. The company requires RFPs from three vendors, and low and high bids must be rejected to determine the selected vendor. Which of the following terms describe this requirement?A . OutsourcingB . Business acquisitionC . Business process changeD . Internal...