Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?
Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?A . EACB . BACC . CPID . ETCView AnswerAnswer: C Explanation: Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 231
Which of the following tools is MOST appropriate for the project team to use to determine the cause of the problem?
One deliverable failed during testing, and this has already happened several times. Which of the following tools is MOST appropriate for the project team to use to determine the cause of the problem?A . Run chartB . Fishbone diagramC . Scatter diagramD . Gantt chartView AnswerAnswer: B Explanation: Reference: Kim...
Which of the following effects is this MOST likely to have on the project?
A new project sponsor has joined the project team, and the constraints on the project have been reprioritized. The project cost was previously the most important factor, but the new sponsor has indicated that meeting a new, shorter deadline is the priority. Which of the following effects is this MOST...
Which of the following conflict resolution techniques has the project manager utilized?
Two team members have concluded that documentation is not required due to the size of the current project. The project manager has encouraged them to align strictly within the process. Which of the following conflict resolution techniques has the project manager utilized?A . SmoothingB . ForcingC . CompromisingD . AvoidingView...
Which of the following is the BEST project management methodology for this requirement?
A customer will have ongoing changes to project requirements. Which of the following is the BEST project management methodology for this requirement?A . WaterfallB . AgileC . PRINCE2D . Bottom-upView AnswerAnswer: B Explanation: Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 310
Which of the following is the FIRST step the project manager should take?
A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule. Which of the following is the FIRST step the project manager should take?A . Assess the risk register’s new items.B . Review the task start and finish dates.C . Obtain additional resources.D . Analyze...
Which of the following describes a burn rate?
Which of the following describes a burn rate?A . The rate at which project documents are disposed.B . The rate at which project personnel leave the project.C . The rate at which the project budget is used.D . The rate at which the timeline increases.View AnswerAnswer: C Explanation: Reference: Kim...
Which of the following factors will MOST likely influence the communication methods used in the project?
A project team is mainly based in a metropolitan area. The team also has members in a remote area, where Internet access is limited and unstable. Which of the following factors will MOST likely influence the communication methods used in the project?A . Personal preferencesB . Technological factorsC . Language...
Assuming an iterative approach, which of the following will be conducted at the end of each iteration?
Assuming an iterative approach, which of the following will be conducted at the end of each iteration?A . SCRUM retrospectiveB . Kickoff meetingC . Budget baselineD . Risk reviewView AnswerAnswer: A Explanation: Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306
Which of the following documents should the project coordinator use?
A project coordinator logs potential events that can affect project constraints, and then records the results of brainstorming of potential strategies. Which of the following documents should the project coordinator use?A . Risk registerB . Issue logC . Communication planD . Status reportView AnswerAnswer: A Explanation: Reference: Kim Heldman, CompTIA...