Which of the following best describes what the PM should work on FIRST?
The PM is preparing for the planning phase kickoff meeting. It is imperative for the team to focus during the meeting on the expected outcomes. Which of the following best describes what the PM should work on FIRST?A . Project charterB . Project scheduleC . Meeting agendaD . Responsibility assignment...
Which of the following characteristics classifies this as a project?
A manufacturer is developing a product that will start in one week. The product has a delivery deadline of 90 days. Which of the following characteristics classifies this as a project?A . RepetitiveB . OngoingC . IterativeD . TemporaryView AnswerAnswer: C
Expenditure tracking helps with cost:
Expenditure tracking helps with cost:A . reportingB . schedulingC . discountingD . floatingView AnswerAnswer: A
A project manager is creating the WBS. In which of the following phases is the project?
A project manager is creating the WBS. In which of the following phases is the project?A . InitiationB . PlanningC . ExecutionD . ClosingView AnswerAnswer: B Explanation: Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 139
Which of the following should the project manager do to resolve this issue?
A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client. Which of the following should the project manager do to resolve this issue?A . Update the scope management plan.B . Modify the project baselines.C...
Which of the following steps should take place NEXT?
A customer has requested additional features for an active project. Which of the following steps should take place NEXT?A . Implement the requested changes.B . Evaluate the impact of the changes.C . Update all project documents.D . Submit the requested changes to the CCView AnswerAnswer: B Explanation: Reference: Kim Heldman,...
Which of the following is a schedule that illustrates the duration of an activity?
Which of the following is a schedule that illustrates the duration of an activity?A . Process diagramB . Ishikawa diagramC . Gantt chartD . Pareto chartView AnswerAnswer: C Explanation: Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 168
Which of the following is the BEST way for the project manager to address the issue?
A project manager is unsure if the quality of a deliverable from a SME meets specifications. Which of the following is the BEST way for the project manager to address the issue?A . Conduct a face-to-face or telephone meeting with the team member.B . Send an email outlining the concerns...
Which of the following documents would contain these items?
During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project. Which of the following documents would contain these items?A . Business caseB . Requirements documentC . Project timelineD . Task planView AnswerAnswer: B Explanation: Reference: Kim Heldman, CompTIA Project+...
Which of the following are characteristics of a project? (Choose two.)
Which of the following are characteristics of a project? (Choose two.)A . OngoingB . TemporaryC . Start and finishD . Achieving a goalE . Consisting of milestonesF . Restricting the budgetView AnswerAnswer: BC Explanation: Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 27