Which of the following can be determined?
An active project has a CPI of 0.92 . Which of the following can be determined?A . The project is currently over budget.B . The project has a budget surplus.C . The project is ahead of schedule.D . The project is behind schedule.View AnswerAnswer: A Explanation: Reference http://smallbusiness.chron.com/project-management-cpi-numbers-mean-35541.html
Which of the following is the BEST risk response strategy?
A project team is in the process of risk planning. One of the team members identifies a weather-related risk, which may cause delivery delays. Which of the following is the BEST risk response strategy?A . ExploitB . EnhanceC . MitigateD . CommunicateView AnswerAnswer: C
Which of the following are characteristics of a project? (Choose two.)
Which of the following are characteristics of a project? (Choose two.)A . OngoingB . TemporaryC . Start and finishD . Achieving a goalE . Consisting of milestonesF . Restricting the budgetView AnswerAnswer: B,C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p.27
Which of the following site types is the PM requesting?
The PM has requested that a project repository be developed. Sensitive information will be available on the site that could affect the project’s success. Only personnel who need to know the information will have access. Which of the following site types is the PM requesting?A . Wiki pageB . IntranetC...
Which of the following is the BEST method to handle this situation?
A member of a CCB notices a change request was not approved by the steering committee . Which of the following is the BEST method to handle this situation?A . Disapprove the change request.B . Evaluate the impact of the change.C . Develop a regression plan.D . Hold the change...
Which of the following charts would indicate the cause and effect of tasks in a project, and for which of the following activities would the chart be used?
Which of the following charts would indicate the cause and effect of tasks in a project, and for which of the following activities would the chart be used?A . Histogram, forecastingB . Ishikawa, quality controlC . Scatter, determining resourcesD . Gantt, leveraging resourcesView AnswerAnswer: B
Which of the following is a characteristics of a matrix organization?
Which of the following is a characteristics of a matrix organization?A . Authority lies solely with the project manager.B . Authority is directed by the project architect.C . Authority is shared between the project manager and project coordinator.D . Authority is shared between functional and project managers.View AnswerAnswer: D Explanation:...
Which of the following make up a company’s portfolio? (Choose two.)
Which of the following make up a company’s portfolio? (Choose two.)A . PeopleB . ProceduresC . ProjectsD . ProcessesE . ProfitF . ProgramsView AnswerAnswer: C,F
Which of the following describes how a project is related to a program?
Which of the following describes how a project is related to a program?A . A program is a combination of multiple projects.B . A program contains an element of the project.C . A program is a part of a project.D . A program uses half of the project’s budget.View AnswerAnswer:...
Which of the following shows projected project expenditures?
Which of the following shows projected project expenditures?A . Work breakdown structureB . Cash flow scheduleC . Cash burn rateD . Budget milestoneView AnswerAnswer: A