Which of the following should the project manager include as part of the lessons learned?
A project manager is providing the lessons learned for a project that ran over budget and produced poor quality deliverables . Which of the following should the project manager include as part of the lessons learned?A . Risk registerB . Post-mortem analysisC . Issue logD . Procurement reportView AnswerAnswer: B...
Which of the following activities should the project manager perform NEXT?
A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change . Which of the following activities should the project...
Which of the following documents can the sponsor review to determine the project’s performance?
Despite receiving regular updates, a sponsor learns a project recently slipped. Which of the following documents can the sponsor review to determine the project’s performance? (Select two.)A . Status reportB . Communication planC . Issue logD . Project scheduleE . Action items listF . Risk registerView AnswerAnswer: A,C
Which of the following would be the BEST approach to resolving the issue?
A PM receives notification that an issue will impact a deliverable on the critical path. The issue is logged with a unique ID and assigned to a team member; however, the team member has not addressed it after a week . Which of the following would be the BEST approach...
Which of the following is a necessary step to record the actual durations?
A project manager needs to track the actual and estimated start and finish dates of all WBS work packages. Which of the following is a necessary step to record the actual durations?A . Establish each WBS work package resource.B . Establish and set the baseline.C . Establish and set the...
Which of the following should the project manager do NEXT?
A project sponsor informs the project manager that the project completion date must be moved one month earlier . Which of the following should the project manager do NEXT?A . Recalculate the critical path, determine the new cost, schedule baselines, and initiate the change request process.B . Recalculate the schedule...
Which of the following strategies is the project manager trying to apply?
A project needs two more months of work to be completed, but the deadline is in 35 days. The project manager heard the company recently hired an experienced person. The project manager scheduled a meeting with the functional manager to negotiate bringing the experienced person to the team . Which...
Which of the following constraints does this impact MOST?
A non-stakeholder approaches the project manager and asks if certain items can be added to a project that was started two months earlier . Which of the following constraints does this impact MOST?A . TimeB . ScheduleC . ScopeD . CostView AnswerAnswer: D
When a project team is productive and effective this phase is known as which of the following?
When forming a project team, there are a number of phases. When a project team is productive and effective this phase is known as which of the following?A . FormingB . NormingC . PerformingD . StormingView AnswerAnswer: C
Which of the following should be included in an effective SOW?
Which of the following should be included in an effective SOW?A . Lessons learnedB . Procurement processC . Corrective action planD . Project objectivesView AnswerAnswer: C