Which of the following project management tools would help?
There is a project in which the team can only meet once every three months. When the team does meet, no one can remember what was discussed and decided upon last time; thus, progress is being delayed . Which of the following project management tools would help?A . Issue logB...
Which of the following should have occurred to prevent this issue?
During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor’s tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the...
Which of the following items BEST describes the unmet objective?
A project manager receives a call from the area regional building department and is informed that, upon inspection, waterlines from public water access to the project building do not meet local material and installation code specifications . Which of the following items BEST describes the unmet objective?A . ScheduleB ....
Which of the following events would MOST likely have triggered the meeting?
A meeting has taken place with quality assurance tram members and the project manager. Which of the following events would MOST likely have triggered the meeting?A . AuditB . Risk register updateC . Task completionD . Resource changeView AnswerAnswer: A
Which of the following actions should the project manager take?
An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs. Which of the following actions should the project manager take?A . Submit a new change request.B . Initiate the...
Which of the following is the MOST likely reason the project manager would be unaware of the team member’s decreased morale?
A project manager is overseeing a multinational project, and team leaders from numerous countries indicate the team members have low morale. Which of the following is the MOST likely reason the project manager would be unaware of the team member’s decreased morale?A . The project manager did not pay attention...
While working on risk ranking, the project team is unsure about the qualitative scales to be used for probability and impact.
While working on risk ranking, the project team is unsure about the qualitative scales to be used for probability and impact. The project manager directs the team to look in the:A . quality plan.B . project management plan.C . risk register.D . process diagram.View AnswerAnswer: A
Which of the following is MOST likely the reason for this?
A company engaged a third-party audit firm to provide regular financial oversight for regulatory compliance and requested a project manager to work with the firm. The PMO declines to assign a project manager and refers to another department within the company . Which of the following is MOST likely the...
Which of the following stages BEST explains this situation?
A new project has just commenced. Project team members are constantly disagreeing on how tasks should be handled and are not getting along well . Which of the following stages BEST explains this situation?A . NormingB . PerformingC . FormingD . StormingView AnswerAnswer: C
Which of the following communication methods and target audiences would a project manager MOST likely select for briefings as required during a business continuity incident?
Which of the following communication methods and target audiences would a project manager MOST likely select for briefings as required during a business continuity incident?A . Email and instant messaging to project team members and the project team members and the project sponsorB . Text messages to and voice conferences...