Which of the following steps should the project manager take FIRST to correct the problem?
A project manager has received numerous complaints from staff concerning poor service provided by a vendor. Which of the following steps should the project manager take FIRST to correct the problem?A . Review the SOW with the vendor and terminate the vendorB . Notify the key stakeholders of the problem...
Which of the following should the project manager do NEXT?
A project manager is informed that a team member would like to enhance the code with an additional function . Which of the following should the project manager do NEXT?A . Submit a change request.B . Evaluate the impact of the change.C . Get approval from the CCE . Communicate...
A project manager is trying to ensure the quality of the design and reduce the number of potential defects. The project manager would like to use the fishbone diagram to perform this analysis.
A project manager is trying to ensure the quality of the design and reduce the number of potential defects. The project manager would like to use the fishbone diagram to perform this analysis. This type of modeling relies on:A . Prioritizing the specific event.B . Variance in the process over...
Which of the following actions should the project manager take?
During a project assessment, a project manager determines the initial project cost estimates were incorrect, and there is not enough budget left, including reserves, to complete the project. Which of the following actions should the project manager take?A . Alert the project sponsor of the situation.B . Contact the customer...
Which of the following conflict resolution techniques has the project manager utilized?
Two team members have concluded that documentation is not required due to the size of the current project. The project manager has encouraged them to align strictly within the process. Which of the following conflict resolution techniques has the project manager utilized?A . SmoothingB . ForcingC . CompromisingD . AvoidingView...
activity?
Which of the following network scheduling techniques is focused mainly on the duration and stack of each activity?A . Program evaluation review techniqueB . Precedence diagramming methodC . Arrow diagramming methodD . Critical path methodView AnswerAnswer: D
Which of the following should the project manager do NEXT?
A subcontractor has submitted design documentation on the deliverable due date, but it will require rework. The activity is on the critical path of the project schedule . Which of the following should the project manager do NEXT?A . Determine the expected duration of the rework and complete a charge...
Which of the following is the BEST reason to conduct regular risk reviews?
Which of the following is the BEST reason to conduct regular risk reviews?A . Risk reviews ensure stakeholders take action on assigned items.B . Risk reviews allow for the identification of response strategies.C . Risk reviews can keep personnel on track with their assigned tasks.D . Risk reviews must be...
Which of the following documents should the project manager consult?
A new project manager is working in an environment where resources report to another supervisor. The project manager is having difficulty with a particular member and wants to escalate the issue . Which of the following documents should the project manager consult?A . Issue logB . RACI chartC . Risk...
Which of the following charts is a mathematical diagram used to values for two variables for a set of data?