Which of the following is the FIRST document the protect manager should review?

A project manager is assigned to an ongoing project. Which of the following is the FIRST document the protect manager should review?A . Project scheduleB . Action itemsC . Project charterD . Communication planView AnswerAnswer: A

March 28, 2022 No Comments READ MORE +

Which of the following documents will the company MOST likely release FIRST?

A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services. Which of the following documents will the company MOST likely release FIRST?A . RFOB . RFIC . RFPD . RFQView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study...

March 28, 2022 No Comments READ MORE +

Which of the following shows projected project expenditures?

Which of the following shows projected project expenditures?A . Work breakdown structureB . Cash flow scheduleC . Cash burn rateD . Budget milestoneView AnswerAnswer: A

March 27, 2022 No Comments READ MORE +

Which of the following should the project manager do to obtain the resources?

The project sponsor has cut the resources required for project completion. The project manager cannot complete the project without additional resources. Which of the following should the project manager do to obtain the resources?A . The project manager should identify and document the reasons for the additional resources in a...

March 27, 2022 No Comments READ MORE +

Which of the following is a necessary step to record the actual durations?

A project manager needs to track the actual and estimated start and finish dates of all WBS work packages. Which of the following is a necessary step to record the actual durations?A . Establish each WBS work package resource.B . Establish and set the baseline.C . Establish and set the...

March 27, 2022 No Comments READ MORE +

Which of the following phases does this describe?

A project manager is working on the project charter. Which of the following phases does this describe?A . InitiationB . PlanningC . ExecutionD . ClosingView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 107

March 27, 2022 No Comments READ MORE +

Which of the following risk strategies should the project manager adopt?

A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the project’s success. Which of the following risk strategies should the project manager adopt?A . ExploitationB . AvoidanceC . AcceptanceD . MitigationView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA...

March 27, 2022 No Comments READ MORE +

In which of the following components of the project plan should this be documented?

A project has just finished performance testing and found that the application can only handle 100 concurrent users where the requirement was to handle 500 concurrent users. In which of the following components of the project plan should this be documented?A . Scope statementB . Issues logC . WBSD ....

March 27, 2022 No Comments READ MORE +

Which of the following is a schedule that illustrates the duration of an activity?

Which of the following is a schedule that illustrates the duration of an activity?A . Process diagramB . Ishikawa diagramC . Gantt chartD . Pareto chartView AnswerAnswer: C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 168

March 26, 2022 No Comments READ MORE +

Which of the following should be the project manager’s NEXT steps?

A vendor is unable to deliver an order by the specified date. Which of the following should be the project manager’s NEXT steps? (Choose two.)A . The project manager should notify the affected project team and, if necessary, adjust the schedule because the project could potentially encounter delays.B . The...

March 26, 2022 No Comments READ MORE +