Which of the following are critical for the project manager to provide?
A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project. Which of the following are critical for the project manager to provide?A . Cost, schedule, organizational chart, and risks/issuesB . Risks/issues,...
Which of the following tasks will take place during this phase?
A project is in the initiation phase. Which of the following tasks will take place during this phase?A . Develop a WBC . Define the project requirements.D . Create a project charter.E . Acquire the project resources.View AnswerAnswer: C
When a project team is productive and effective this phase is known as which of the following?
When forming a project team, there are a number of phases. When a project team is productive and effective this phase is known as which of the following?A . FormingB . NormingC . PerformingD . StormingView AnswerAnswer: C
Which of the following tasks are on the critical path?
There are four parallel paths on a network diagram. The summary duration of each path is below: A, C, G: 10 weeks A, B, F: 8 weeks D, E, H: 12 weeks D, B, F: 7 weeks Which of the following tasks are on the critical path?A . A, C,...
Which of the following risk strategies should the project manager adopt?
A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the project’s success. Which of the following risk strategies should the project manager adopt?A . ExploitationB . AvoidanceC . AcceptanceD . MitigationView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA...
In which of the following phases is the project?
A project manager is creating the WBS. In which of the following phases is the project?A . InitiationB . PlanningC . ExecutionD . ClosingView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 139
Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?
Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?A . Project manager and project schedulerB . Project coordinator and project sponsorC . Project champion and project schedulerD . Project stakeholders and project teamView AnswerAnswer: D...
Which of the following would the project manager MOST likely do?
A project team member highlights to the project manager that expensive licensing for critical software in use across the project may expire before the completion project. Which of the following would the project manager MOST likely do?A . Place a risk on the risk register and arrange a risk review...
Which of the following should the project manager do NEXT?
A project in the execution phase is over budget, and tasks on the critical path are on schedule. Which of the following should the project manager do NEXT?A . Update the project management plan.B . Issue a change request.C . Revise the project charter.D . Evaluate the impact to the...
In which of the following categories does a business process change fit?
In which of the following categories does a business process change fit?A . Project changeB . Organizational changeC . General changeD . Departmental changeView AnswerAnswer: B Explanation: “Business process changes typically occur within the organization. An example of a business process change is automating a process that previously was performed...