Which of the following were MOST likely missed during project planning?
A department manager asks a project manager about the status of a project that has only a few employees from the department assigned to it. Which of the following were MOST likely missed during project planning?A . Issue log and process diagramB . Resource analysis and Gantt chartC . Stakeholder...
Which of the following is the MOST expedient communication method, assuming the question can be resolved quickly?
A project team is composed of numerous team members who are located throughout a country. All personnel have identified core business hours. A team engineer based in a machine shop has a question during business hours for the project manager, who is located at a different facility. Which of the...
Which of the following should the project manager do NEXT?
A project manager received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes. Which of the following should the project manager do NEXT?A . Gain approval for the changes.B . Identify the approval authority.C . Implement the changes.D . Create an...
Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?
Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?A . EACB . BACC . CPID . ETCView AnswerAnswer: C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 231
Which of the following would BEST communicate the need for a WBS to the other managers?
A project manager wants to introduce the practice of a WBS to the PMO, but the other managers believe this will create extra work. Which of the following would BEST communicate the need for a WBS to the other managers? (Select TWO).A . Using the WBS will help prevent work...
Which of the following is the MOST effective method for providing these updates?
A project requires daily status updates. Which of the following is the MOST effective method for providing these updates?A . BacklogB . StandupC . KickoffD . RetrospectiveView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306
In which of the following components of the project plan should this be documented?
A project has just finished performance testing and found that the application can only handle 100 concurrent users where the requirement was to handle 500 concurrent users. In which of the following components of the project plan should this be documented?A . Scope statementB . Issues logC . WBSD ....
Which of the following are characteristics of a project? (Choose two.)
Which of the following are characteristics of a project? (Choose two.)A . OngoingB . TemporaryC . Start and finishD . Achieving a goalE . Consisting of milestonesF . Restricting the budgetView AnswerAnswer: B,C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 27
Which of the following conflict resolution techniques is the project manager using?
A project sponsor and Chief Information Officer (CIO) disagree about how to release the final deliverables to the market. The sponsor wants to do a massive product release, while the CIO wants to be extremely cautious and add more time for testing and defect resolution. The project manager works with...
Which of the following phases does this describe?
A project manager is working on the project charter. Which of the following phases does this describe?A . InitiationB . PlanningC . ExecutionD . ClosingView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 107
 
	