Which of the following would be used to communicate a high level description of a major change that involved significant cost and risk to theorganization?

Which of the following would be used to communicate a high level description of a major change that involved significant cost and risk to theorganization?
A . Change proposal
B . Change policy
C . Service request
D . Risk register

Answer: A