Which statement about the ‘change control’ practice is CORRECT?

Which statement about the ‘change control’ practice is CORRECT?
A . Standard changes are those that need to be scheduled, assessed and authorized following a standard process
B . Normal changes are triggered by the creation of a change request which can be created manually or automated
C . Assessment and authorization of normal changes should be expedited to ensure they can be implemented quickly
D . There should be a separate change authority for standard changes which includes senior managers who understand the risks involved

Answer: B

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments