When should the effectiveness of a problem workaround be assessed?
When should the effectiveness of a problem workaround be assessed?
A . Whenever the workaround is used
B . Whenever the problem is resolved
C . Whenever the workaround becomes a known error
D . Whenever the problem is prioritized
Answer: A