Which type of analysis should the project manager use in this instance?

A project manager is developing the risk register and works with the team to analyze risks and determine their probability and impact. There is valuable historical data available that may be used to simulate the overall risk outcome.

Which type of analysis should the project manager use in this instance?
A . Check list analysis
B. Cause and effect
C. Specialized meeting
D. Quantitative analysis

Answer: D

Explanation:

In this instance, the project manager should use quantitative analysis to simulate the overall risk outcome. Quantitative analysis techniques, such as Monte Carlo simulation or decision tree analysis, can be used to model the combined effect of individual risks on project objectives. By leveraging historical data, the project manager can generate more accurate and reliable risk assessments, which can help inform risk response strategies and improve project decision-making.

Latest PMI-RMP Dumps Valid Version with 115 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments