How should the project manager handle this situation?

At an oil and gas company, a major unified management information system is to be implemented. The project manager noted that risks gathered from the organization’s business functions are not properly identified and categorized, making it difficult to develop an effective risk response.

How should the project manager handle this situation?
A . Outsource conducting the risk response plan to risk consultants.
B. Ask functional managers to improve their risk register and process.
C. Adjust the risk response plans to effectively handle the identified risks.
D. Coach the functional groups on how to properly conduct the process.

Answer: D

Explanation:

The project manager should provide guidance and coaching to the functional groups on how to properly identify and categorize risks. This will help improve the quality of the risk register and ensure an effective risk response plan can be developed.