What two items should the risk manager have their team review in order to prepare for an upcoming risk identification workshop?

A risk manager was recently hired to assist with a mid-sized infrastructure project. The risk manager becomes aware that they have an inexperienced project team.

What two items should the risk manager have their team review in order to prepare for an upcoming risk identification workshop? (Choose two.)
A . Scope of work and requirements
B. Monte Carlo analysis from a similar project
C. List of pre-approved contractors
D. Organization chart for city permit department
E. Risk management plan

Answer: A,E

Explanation:

The risk manager should have their team review the scope of work and requirements to ensure they understand the project’s objectives and deliverables. Additionally, reviewing the risk management plan will help the team understand the risk management process, roles, and responsibilities, and prepare for the risk identification workshop.