What should the project manager do regarding those risks?

The project sponsor asks the project manager about the accuracy of the project data. The project manager realizes that some risks have not been updated recently.

What should the project manager do regarding those risks?
A . Review the assumptions analysts
B. Conduct a checklist analysis on each risk
C. Create a risk response plan tor those risks
D. Review the risk register to check for the new risks

Answer: D

Explanation:

If the project manager realizes that some risks have not been updated recently, they should review the risk register to check for new risks and ensure that all risks are accurately documented and updated.