What should the team perform in this scenario?

The project team is updating the risk register with the minimum acceptable level of exposure and impact for each risk. The team also wants to determine if they have reached the maximum level of exposure before they escalate the risk.

What should the team perform in this scenario?
A . Quantitative risk analysis
B. Risk response planning
C. Monitor and control risks
D. Risk urgency assessment

Answer: A

Explanation:

Quantitative risk analysis helps determine the minimum acceptable level of exposure and impact for each risk. It also helps to understand if the maximum level of exposure has been reached before escalating the risk. ( Explanation:

Reference: PMBOK Guide, 6th Edition, p. 423)