A new risk manager is assigned to an ongoing project, what should the new risk manager dofirst to assess the project environment?

A new risk manager is assigned to an ongoing project, what should the new risk manager dofirst to assess the project environment?
A . Review potential next steps with the project team.
B. Review the scope of work to determine the prescribed project methodology.
C. Review the policies and practices that are outlined in the risk management plan.
D. Review the contract and determine the resources and project funding.

Answer: C

Explanation:

When a new risk manager is assigned to an ongoing project, their first step should be to review the existing risk management plan to understand the current policies, practices, and strategies in place.