What should the project manager do next?

Stakeholder deliverable reviews will start soon and additional work is expected to resolve any issues or required adjustments. Budget overruns during execution have put serious constraints on the remainder of the project’s budget.

What should the project manager do next?
A . Request a budget relief using the management reserve.
B. Conduct a risk reassessment and reserve analysis.
C. Review the consequences of potential changes.
D. Coach stakeholders on risk identification practices.

Answer: B

Explanation:

The project manager should reassess the risks and analyze the reserve to determine if any adjustments can be made to accommodate the expected additional work. This will help in identifying potential budget-saving measures and making informed decisions on how toproceed.