What action should the risk manager propose?

The project manager wants to use an objective method to evaluate the key project risks and develop response plans.

What action should the risk manager propose?
A . Ask the team to perform an earned value analysis.
B. Review the lessons learned from other projects.
C. Ask the team to prepare a Monte Carlo analysis.
D. Ask the risk expert to perform a PESTLE evaluation.

Answer: C

Explanation:

The action that the risk manager should propose is to ask the team to prepare a Monte Carlo analysis. This is a statistical technique that can be used to model the probability of different outcomes in a project. By performing a Monte Carlo analysis, the project manager can objectively evaluate key project risks and develop response plans based on this analysis.