What should the project risk manager monitor closely?

A project has a significant impact on an organization. Multiple stakeholders expressed concerns regarding the overall project risk during construction of the risk management plan, and they agreed that the risk appetite is low.

What should the project risk manager monitor closely?
A . Risk thresholds
B. Risk response strategies
C. Risk management reports
D. Risk breakdown structure (RBS)

Answer: A

Explanation:

The project risk manager should monitor risk thresholds closely, as they represent the organization’s risk appetite. In a project with a low risk appetite, it is essential to ensure that risks are managed within the defined thresholds to address stakeholders’ concerns and maintain their confidence in the project’s success.