After performing a detailed analysis, what should the risk manager do?

A supplier Is delayed in delivering fuel for a project. The project manager anticipated this risk and is requesting fuel from another supplier. When speaking with the other supplier, a new risk appears because fulfilling the order will cause delays with several other projects.

After performing a detailed analysis, what should the risk manager do?
A . Escalate the problem to the project sponsors.
B. Execute the approved risk response plan.
C. Negotiate with the supplier to resolve the problem.
D. Assign a team member to update the issue leg.

Answer: B

Explanation:

The risk manager should execute the approved risk response plan, which should have been developed during the risk management process. This plan outlines the actions to be taken in response to specific risks and ensures that the project team is prepared to address potential issues.

Latest PMI-RMP Dumps Valid Version with 115 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments