Which document will need to be updated?

A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.

Which document will need to be updated?
A . Lessons learned
B. Contingency register
C. Risk register
D. Issue log

Answer: A

Explanation:

When closing risks as part of the closing process, it is important to update the lessons learned document. This document captures the knowledge and experience gained during the project and can be valuable for future projects.