What three artifacts should the project manager consult or review during this process?

A project lihat was in the execution phase for the last six months was put on hold and was eventually cancelled after numerous scope related challenges. It was decided to re-plan the scope and divide the project into multiple projects to have better insight into end objectives. As part of the project start up. the project manager is developing the risk planning for the project.

What three artifacts should the project manager consult or review during this process? (Choose three.)
A . Project contracts
B. Lessons learned registers from analogous projects
C. Risk register
D. Risk management plan
E. Code of regulations

Answer: A,B,D

Explanation:

The project manager should consult or review project contracts, lessons learned registers from analogous projects, and the risk management plan to develop an effective risk planning for the project.

Latest PMI-RMP Dumps Valid Version with 115 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments