What type of risk is this?

A project manager is working on a construction project. Based on past experience, the project manager identifies a risk that a supplier of a critical material may not deliver on time. The project manager has already accounted for this risk in the risk management plan. If this risk materializes, the project manager plans to procure the material from a different supplier. A potential risk in this plan is that there may be differences in the material provided by the first and second supplier.

What type of risk is this?
A . Residual risk
B. Primary risk
C. Secondary risk
D. Normal risk

Answer: C

Explanation:

This is a secondary risk because it is a risk that arises as a direct result of

implementing a risk response (in this case, procuring material from a different supplier).

Latest PMI-RMP Dumps Valid Version with 115 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments