What will help calculate the impact?

Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.

What will help calculate the impact?
A . Risk analysis
B. Risk identification
C. Risk treatment
D. Risk evaluation

Answer: A

Explanation:

Risk impact assessment involves calculating the impact of identified risks. Risk analysis is the process of examining, estimating, and evaluating the impact of risks, which helps in calculating the impact (Reference: PMBOK Guide, 6th Edition, p. 417)