What should the project manager do next?

While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.

What should the project manager do next?
A . Identify secondary or residual risks for associated risk plans.
B. Develop risk response plans for all identified risks.
C. Update the communications management plan to avoid future issues
D. Monitor and control secondary and residual risks in the risk register.

Answer: D

Explanation:

The project manager should monitor and control secondary and residual risks in the risk register. This will ensure that any new risks identified during the implementation of the risk response plan are captured and managed effectively. Monitoring and controlling risks is acontinuous process that helps in identifying, analyzing, and planning for new risks as well as updating the risk register as needed.

Latest PMI-RMP Dumps Valid Version with 115 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments