What should the team perform in this scenario?

The project team is updating the risk register with the minimum acceptable level of exposure and impact for each risk. The team also wants to determine if they have reached the maximum level of exposure before they escalate the risk. What should the team perform in this scenario?A . Quantitative...

June 1, 2023 No Comments READ MORE +

How should the project manager address this concern?

Several key stakeholders approach the project manager with concerns. The stakeholders have received feedback from local businesses that have reported a reduction in customers because of construction activities at the worksite, and they plan to submit a claim to the municipality to fine the project manager's company. How should the...

June 1, 2023 No Comments READ MORE +

What should the risk owner do?

An organization with a large computer network identified a potential cyber security threat. Although certain measures were implemented to avoid the risk, the cyber security threat occurs. The measures were partially successful and a new unforeseen risk emerges. What should the risk owner do?A . Develop an efficient network protection...

June 1, 2023 No Comments READ MORE +

What will help calculate the impact?

Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted. What will help calculate the impact?A . Risk analysis B. Risk identification C. Risk treatment D. Risk evaluationView AnswerAnswer: A Explanation: Risk impact assessment involves calculating...

May 31, 2023 No Comments READ MORE +

What should the risk manager do?

A risk manager has been assigned to a project constructing a chemical laboratory. Unfamiliar with chemical laboratories, the risk manager is unsure of where to start objectively identifying risks. What should the risk manager do?A . Import a risk register from other industry chemical laboratories. B. Define chemical laboratory safety...

May 30, 2023 No Comments READ MORE +

Which document will need to be updated?

A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated. Which document will need to be updated?A . Lessons learned B. Contingency register C....

May 30, 2023 No Comments READ MORE +

How should the project manager work with these risk handling strategies?

A project manager wants to work on understanding the project risks. The project manager works with the integrated project team to develop the risk handling strategies for the identified risks. How should the project manager work with these risk handling strategies?A . Review and revise the strategies periodically. B. Implement...

May 29, 2023 No Comments READ MORE +

What analysis is currently being used?

The risk manager also serves as a facilitator for a project and realizes the project team members have biases impacting how they perceive risks. What analysis is currently being used?A . Quantitative risk analysis B. Force field analysis C. Qualitative risk analysis D. Stakeholder analysisView AnswerAnswer: C Explanation: The analysis...

May 28, 2023 No Comments READ MORE +

What should the project manager do next?

A project manager works on a long-term and high visibility project at an organization that has a low risk appetite towards this project due to its impact on the company's business. The project sponsors follow up weekly with the project manager, who was just informed by one of the risk...

May 28, 2023 No Comments READ MORE +

Who should the project manager hold accountable for missing the risks?

A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognizes that some key secondary risks have not been considered. Who should the project manager hold accountable for missing the risks?A ....