Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

Who determines when it is appropriate to update the Sprint Backlog during a Sprint?
A . The Project Manager.
B . The Development Team.
C . The Scrum Team.
D . The Product Owner.

Answer: B