Who creates the definition of “Done”?

Who creates the definition of “Done”?
A . The Scrum Master as he/she is responsible for the Development Team’s productivity.
B . The Scrum Team, in a collaborative effort where the result is the common denominator of all members’ definition.
C . The Product Owner as he/she is responsible for the product’s success.
D . The development organization (or Development Team if none is available from the development organization).

Answer: D

Latest PSM I Practice Questions with 197 Q&As

Updated Study Material | Instant Download | Detailed Answers and Explanations

Subscribe
Notify of
guest
2 Comments
Tola
Tola
4 years ago

The 2020 scrum guide says –

“If the Definition of Done for an increment is part of the standards of the organization, all Scrum Teams must follow it as a minimum. If it is not an organizational standard, the Scrum Team must create a Definition of Done appropriate for the product.”

Roland Kim
Roland Kim
5 years ago

correct answer is B not D