The length of a Sprint should be:

The length of a Sprint should be:
A . Short enough to keep the business risk acceptable to the Product Owner.
B . Short enough to be able to synchronize the development work with other business events.
C . No more than one calendar month.
D . All of these answers are correct.

Answer: D