Which of the following statements is most accurate?

During the Sprint Retrospective a Scrum Team has identified several high priority process improvements.

Which of the following statements is most accurate? (Choose the best answer.)
A . The Scrum Team may add items to the Sprint Backlog for the next Sprint.
B . The Scrum Team should choose at least one high priority process improvement to place in the Product Backlog.
C . The Scrum Team should decline to add a process improvement to the Sprint Backlog when things are
running smoothly.
D . The Scrum Master selects the most important process improvement and places it in the Sprint Backlog

Answer: A

What techniques could the Scrum Master use when the Scrum Team gets caught in an internal disagreement about which agile practices to apply? (Choose the best two answers.)

What techniques could the Scrum Master use when the Scrum Team gets caught in an internal disagreement about which agile practices to apply? (Choose the best two answers.)
A . Involve the complete Scrum Team in making a decision.
B . Use coaching techniques; such as open QUESTION NO:s and active listening.
C . Ask an external agile coach what they recommend.
D . Ask team members to take the issue up with to the company’s Human Resources department.

Answer: A,B

If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team?

If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team?
A . Its productivity is likely to decrease.
B . Its productivity is likely to stay the same.
C . Its productivity is likely to increase.

Answer: A

When many Scrum Teams are working on a single product, what best describes the Definition of Done?

When many Scrum Teams are working on a single product, what best describes the Definition of Done?

(Choose the best answer.)
A . Each Scrum Team defines and uses its own. The differences are discussed and reconciled during a
hardening Sprint.
B . The Scrum Masters from each Scrum Team define a common Definition of Done.
C . Each Scrum Team uses its own, but must make their definition clear to all other teams so the differences are known.
D . All Scrum Teams must have a Definition of Done that makes their combined work potentially releasable.

Answer: D

When many Development Teams are working on a single product, what best describes the definition of “Done”? (Choose the best answer.)

When many Development Teams are working on a single product, what best describes the definition of “Done”? (Choose the best answer.)
A . Each Development Team defines and uses its own. The differences are discussed and reconciled during a hardening Sprint.
B . It depends.
C . Each Development Team uses its own but must make their definition clear to all other teams so the differences are known.
D . All Development Teams must have a definition of “Done” that makes their combined work potentially releasable.

Answer: D

What factors likely led to this?

At the seventh Sprint Review, the stakeholders are disappointed and angry. They have determined that the product or system being built will not meet their needs and will cost more than they are willing to spend.

What factors likely led to this? (Choose two.)
A . The Project Management Office (PMO) has not been engaged adequately.
B . The Product Owner has not been keeping the stakeholders aware of the progress of the project.
C . The stakeholders haven’t been using the Sprint Reviews to inspect and evaluate progress.
D . The stakeholders were not allowed to enter the development area.

Answer: A,B

What would be good advice to give the Product Owner?

A Development Team asks their Product Owner to re-order the Product Backlog. The team is waiting for an external supplier to deliver a specific software component. Without that component there won’t be enough work in the next Sprint to occupy the full team. The Product Owner asks the Scrum Master for help.

What would be good advice to give the Product Owner?
A . Remind the Product Owner that his primary concern is the flow of value reflected in the ordering of the Product Backlog.
B . Tell the Product Owner to re-order the Product Backlog so the work involving the external component can be planned in a separate sprint.
C . Tell the Product Owner that the Product Backlog should be ordered to maximize utilization of the Development Team.

Answer: A