- All Exams Instant Download
Which two things should the Development Team do during the first Sprint? (Choose two.)
Which two things should the Development Team do during the first Sprint? (Choose two.)
A . Make up a plan for the rest of the project.
B . Analyze, describe, and document the requirements for the subsequent Sprints.
C . Develop at least one piece of functionality.
D . Analyze, design, and describe the complete architecture and infrastructure.
E . Create an increment of potentially releasable software.
Answer: C,E
Latest PSM I Dumps Valid Version with 197 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments